AERCO ProtoNode Gateway
User Manual
Page 24 of 126 AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913 OMM-0080_0H
11/06/2014 Ph.: 800-526-0288 GF-129
4.2 Wiring the ProtoNode LER Field Port to a LonWorks Network
Connect the ProtoNode to the field network with the LonWorks terminal using a twisted pair
non-shielded cable. LonWorks has no polarity.
Figure 4-3: ProtoNode LER LonWorks Field Port Terminal
4.3 Power-Up of ProtoNode RER or ProtoNode LER
Apply power to ProtoNode. Ensure that the power supply used complies with the specifications
provided in Appendix A.1. Ensure that the cable is grounded using the “Frame-GND” terminal.
ProtoNode accepts either 9-30VDC or 12-24 VAC.
Table 4-2: Power Requirement for ProtoNode at 9V through 30 VDC or 12-24 VAC
ProtoNode Family
Current Draw Type
Figure 4-4: Power Connections
Table 4-3: ProtoNode Power Connections